Question.41
Your organization is developing and deploying an application on Google Cloud. Tracking your Google Cloud spending needs to stay as simple as possible.

What should you do to ensure that workloads in the development environment are fully isolated from production workloads?

(A) Apply a unique tag to development resources
(B) Associate the development resources with their own network
(C) Associate the development resources with their own billing account
(D) Put the development resources in their own project
41. Click here to View Answer

Correct Answer: D

 

Question.42
Your company is running the majority of its workloads in a co-located data center. The workloads are running on virtual machines (VMs) on top of a hypervisor and use either Linux or Windows server editions. As part of your company’s transformation strategy, you need to modernize workloads as much as possible by adopting cloud-native technologies. You need to migrate the workloads into Google Cloud.

What should you do?

(A) Export the VMs into VMDK format, and import them into Compute Engine
(B) Export the VMs into VMDK format, and import them into Google Cloud VMware Engine
(C) Migrate the workloads using Migrate for Compute Engine
(D) Migrate the workloads using Migrate for Anthos
42. Click here to View Answer

Correct Answer: D

 

Question.43
Your organization is running all its workloads in a private cloud on top of a hypervisor. Your organization has decided it wants to move to Google Cloud as quickly as possible. Your organization wants minimal changes to the current environment, while using the maximum amount of managed services Google offers.

What should your organization do?

(A) Migrate the workloads to Google Cloud VMware Engine
(B) Migrate the workloads to Compute Engine
(C) Migrate the workloads to Bare Metal Solution
(D) Migrate the workloads to Google Kubernetes Engine
43. Click here to View Answer

Correct Answer: B

 

Question.44
Your organization is releasing its first publicly available application in Google Cloud. The application is critical to your business and customers and requires a 2- hour SLA.

How should your organization set up support to minimize costs?

(A) Enroll in Premium Support
(B) Enroll in Enhanced Support
(C) Enroll in Standard Support
(D) Enroll in Basic Support
44. Click here to View Answer

Correct Answer: B

 

Question.45
Your organization offers public mobile apps and websites. You want to migrate to a Google Cloud-based solution for checking and maintaining your users’ usernames and passwords and controlling their access to different resources based on their identity.

Which should your organization choose?

(A) VPN tunnels
(B) Identity Platform
(C) Compute Engine firewall rules
(D) Private Google Access
45. Click here to View Answer

Correct Answer: B