Question.51 In which of the following phases of the DITSCAP process does Security Test and Evaluation (ST&E) occur? (A) Phase 2 (B) Phase 3 (C) Phase 1 (D) Phase 4 |
51. Click here to View Answer
Correct Answer: B
Question.52 You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process. Which one of the following is NOT an output of the risk response planning? (A) Risk-related contract decisions (B) Project document updates (C) Risk register updates (D) Organizational process assets updates |
52. Click here to View Answer
Correct Answer: D
Question.53 Thomas is a key stakeholder in your project. Thomas has requested several changes to the project scope for the project you are managing. Upon review of the proposed changes, you have discovered that these new requirements are laden with risks and you recommend to the change control board that the changes be excluded from the project scope. The change control board agrees with you. What component of the change control system communicates the approval or denial of a proposed change request? (A) Configuration management system (B) Change log (C) Scope change control system (D) Integrated change control |
53. Click here to View Answer
Correct Answer: D